_____ ______ is the tool used to identify, evaluate, manage and resolve changes during design, procurement and construction.

Prepare for the DBIA Exam 2 with engaging flashcards and comprehensive multiple choice questions, complete with hints and explanations. Ace your exam with confidence!

Multiple Choice

_____ ______ is the tool used to identify, evaluate, manage and resolve changes during design, procurement and construction.

Explanation:
In this context, a formal change control process is used to identify, evaluate, manage, and resolve changes that arise during design, procurement, and construction. It provides a structured workflow: a change request is submitted, an impact analysis is conducted on scope, cost, schedule, safety, and risk, options are considered, approvals are obtained, the change is implemented, and all decisions are documented for traceability. This approach helps keep the project baseline intact, supports consistent decision-making, and reduces disputes by ensuring every modification is analyzed and approved before being enacted. Risk assessment looks at potential negative events and their likelihood or consequence, not the active mechanism for handling modifications. Value engineering focuses on improving function and cost efficiency but isn’t a formal process for managing changes across design and construction. Trend management monitors patterns and data over time, rather than controlling how changes are identified, evaluated, and executed.

In this context, a formal change control process is used to identify, evaluate, manage, and resolve changes that arise during design, procurement, and construction. It provides a structured workflow: a change request is submitted, an impact analysis is conducted on scope, cost, schedule, safety, and risk, options are considered, approvals are obtained, the change is implemented, and all decisions are documented for traceability. This approach helps keep the project baseline intact, supports consistent decision-making, and reduces disputes by ensuring every modification is analyzed and approved before being enacted.

Risk assessment looks at potential negative events and their likelihood or consequence, not the active mechanism for handling modifications. Value engineering focuses on improving function and cost efficiency but isn’t a formal process for managing changes across design and construction. Trend management monitors patterns and data over time, rather than controlling how changes are identified, evaluated, and executed.